Thank you, Deputy.
Mr. Chair, with respect to the $28 million that is available to fund other initiatives because of the reprofiling, there was about a six-month delay in getting effective project approval to proceed with the construction of the centres. As a consequence, the spending has been pushed to the right. This $28 million simply reflects that delay. It has nothing to do with a backing off on the commitment. It's simply a delay in the approval process, which affected the project schedule.