You mentioned the joint support ship. One of the lessons from that.... That procurement was cancelled because of the procurement strategy, which had us dealing with two design teams. Once we put out the request for proposal, we weren't able to get into detailed cost-capability trade-offs with them until they came back with their bids. By the time they came back with their bids, their bids had exceeded the initial budget that had been set.
The government announced the NSPS in 2010, and the umbrella agreements were let in 2011 with Irving on the east coast and Seaspan on the west, which pretty much re-baselined the delivery dates for the joint support ship, the Arctic offshore patrol ship, and the Canadian surface combatant. I can tell you now that the Arctic offshore patrol ship is on time based on that schedule, and with regard to the joint support ship, we think there is perhaps a one-year delay from when we initially thought we would take receipt of a joint support ship.