Thank you, sir, for the question.
Yes, we're on track. Again, it's a service to be delivered in the fall of 2017. Federal Fleet Services, as the company is now called, with whom we are in contract, for whom the Davie shipyard is a subcontractor, is very open. We're there monthly and have a third party overseeing it.
They are telling us quite openly that a lot of what remains is the disassembled part of the ship, the MV Asterix, starting to pull it together. At the end of the winter of 2017, they will be bringing over what we call a major piece of the structure, the house, which has been built in Scandinavia. It will be coming over and put onto the ship.
They are reflecting that there is risk ahead, as there is in anything this complex, but are very open. Currently, notwithstanding some schedule risks that we see in all our projects, it is on track to be able to provide that service to the navy in the fall of 2017.