There's been a lot of talk about air defence for the land force. This project suffered an extraordinary delay because it was poorly funded. I don't want to give too much information about my role as an acquisitions adviser, but I can say that, when I reviewed this project within the department, it was extremely frustrating, because it was needed, but there was a lack of funding to move forward. That's one example.
Then there are trucks, which are a basic component. You've seen that a truck project is now being split in two, simply to make sure they move forward with the budget they have. They're setting aside the other part, which involves armoured vehicles, because they're still waiting for other funding before they move forward. Unfortunately, this is very common.