I will start and then let Anne-Marie answer, because she's the one who actually leads the bid team at Bombardier that receives the proposals from all around the world.
Clearly, there was a flaw in the process here. PSPC went out with an RFI, which we answered in good faith. As a very responsible company, we said we can do A, B, C, D...all the 13 criteria they had. We said we were capable of doing it. Our partner, GDMS, was also capable of doing the work with us.
To answer your first question, yes, there was a flaw in the process because, since that, we haven't heard from anybody. There's been nobody. They are referring now.... It's a new thing that we heard about for the first time a couple weeks ago. There was a study done by engineers who have never knocked on our door to ask any questions. I don't know how they can appreciate and make comments in a report about our capability, as we don't know these guys.
It was the same thing. We never had anybody from PSPC—an engineer who is knowledgeable—who could say whether Bombardier could do it or not.
I'll let Anne-Marie add about other countries' processes versus ours.