Thank you, Mr. Chair.
I'd like to welcome our witnesses back to committee.
I want to go down the path a bit on the maritime multi-mission aircraft.
PSPC published a timeline on this, so 2021-22 would start the options analysis, 2023-24 would start the definition, 2027-28 would start the implementation of the contract, 2032-33 would be the initial delivery of the first of the aircraft, and the last of the new aircraft would be delivered in 2037-38.
However, if you look at what's happened, in February 2022, you guys did the request for information from potential contractors with an April 1 deadline. By March 2023, you guys had already sent a letter of request to purchase the Boeing P-8s.
What happened, because we're not on the same timeline that was originally laid out? I'm not against speed. I think speed is one of the things we've been talking about here. It seems to be that some steps were missed.