Mr. Chair, in his comment, Deputy Minister Matthews said that they were trying to stay within the 3% range and that they're more concerned from the department on the Canadian Armed Forces side about projects. We are unaware of anywhere you can find a list of those projects, so I would ask that he table that information with the committee.
Right now, procurement of capabilities, for example, was 21% short, and that's $1 billion. Sustainable bases, information technology systems and infrastructure are another $200 million short, which is also outside of that 3%. If you could submit that project by project to the committee for this study, it would be very worthwhile.