If you want to take a look at a very practical operation at the moment, it's the refurbishment at Bruce. They're doing the two units at Bruce A, units 1 and 2, plus some upgrades at units 3 and 4 once they've done units 1 and 2. That's a $4.25 billion operation, which will yield a price of about 6.5ยข a kilowatt for the movement back on of 1,500-plus megawatts at Bruce units 1 and 2.
On May 16th, 2007. See this statement in context.