There is no documentation that specifically says that was the requirement. There were seven safety system upgrades, of which EPS was one. EPS was designed to power the other safety system upgrades to give a seismically qualified power system to those upgrades so that their hazards qualified. In addition, EPS was to be connected to the pumps.
On February 5th, 2008. See this statement in context.