First of all, let me try to address the two press releases. There was one on November 30—you are correct—and another one in December. In the December press release we actually did reveal what we felt the financial impact would be on our company.
The reason for the difference as you go through time is that the picture was in flux. On November 22 we weren't sure how long it would be before NRU would restart. We left that issue between Atomic Energy of Canada and the Canadian Nuclear Safety Commission to decide.
This was a regulatory issue, an issue between the licensor and the licensee. We did not intervene in that at all. So we did not put pressure on AECL and did not put pressure on the CNSC to restart. We did want to understand process, yes, because some of that would help us in our production planning in trying to outsource material from other suppliers.
Does that answer your question?