More or less, but let me elaborate on it a little bit.
First of all, we started advising customers on November 22. We took action right away. The situation, as I mentioned, was fluid, so there was no clear timeline as to when the NRU reactor would be restarted. So there was a dialogue under way between the regulator and AECL to try to determine what had to be done, what had to be effected, to get the NRU back up.
Even going to November 30, the actual restart date was not clear. At about November 30, we had to move. We had to publicly inform our shareholders and stakeholders of what the situation was, even though after that the movement continued.