The project ran into some problems, prior to commissioning in 2000, around the shut-off mechanisms for the control rods. They were safety issues, essentially. This was before the coefficient of reactivity issue.
I'm going to ask Mr. Malkoske to comment, because he was there at the time and I wasn't.