There is a three-week planned shutdown at this time. Discussions are still continuing with regard to those plans. But that is where other reactors have to come into play, and the scheduling of the reactors has been an issue that was raised not only in the last few days but has been raised for the past month, including by the nuclear energy agency, to achieve the best possible balance. These reactors do have to undergo some outages, because it's not prudent to operate them longer than what they are licensed to do.
The reactor operators are working together in a forum called the Association of Imaging Producers and Equipment Suppliers try to align those schedules as well as possible. But there will be some periods where the supply will be tight, and that is a fact.