Thank you for the question. We believe this process is being managed in a very thorough and careful way, with a goal to having the highest probability of the re-licensing application being successful in October of 2011.
We are working very carefully and closely with CNSC staff so that there are clear expectations as to what we must do to satisfy their licensing requirements and to understand that far enough in advance that we can actually do the work in a systematic and thorough way.
As it relates to our own internal governance process, we have both a project risk review committee and a science and technology nuclear oversight committee of our board of directors. I, as the CEO, with Bill, as the chief nuclear officer, and Michael, as the head of operations for our refurbishment projects are collectively accountable to those directors of our corporation. We have very, very thorough and regular reviews.
We do not intend to let any of our regulatory commitments fall by the wayside because of that October 2011 deadline.