Yes, I'll give you a really good example. We used to do a lot of work on Victoria Island, where there is a boundary that came right through the middle of a project. On one side it was Nunavut, and on the other side was NWT. For the same permit, just to do some drilling of several targets—which is fairly low impact, with a small footprint—what took us, say, three months and about $5,000 took us 14 months on the other side and probably cost closer to $80,000 or $90,000, just to get the very same permit.
So it's a very significant difference.