Thank you, Mr. Chair.
Minister, I'd like to address the NEB's dealings with the Line 9 reversal project. I know you were in Montreal on Friday.
On the 25th and 27th of October, 2011, NEB inspectors inspected pumping stations on the line. From what they found in 2011, currently the Westover and Terrebonne pump stations are non-compliant. Both stations' emergency shutdown systems are non-compliant. In May 2012 Enbridge made an assurance of voluntary compliance to come into compliance. It was supposed to do a corrective action plan by October 2012. Enbridge asked for an extension. It was given until April 15 of this year to come up with a corrective action plan.
Right now we have two major pumping stations that are not compliant. They don't have the emergency shutdown systems they are supposed to. Of the 125 pump stations, 117 are currently non-compliant. This has been the case since 2011. Has Enbridge submitted its corrective action plan for this non-compliance?