Thank you.
The answer to your question is that there are different levels. First, there is the interconnection for a utility-sized power plant. Right now the standard for interconnection is being reviewed in Canada. We are participating in this activity to review the distributed energy generation interconnection standard.
It is true that, at the utility scale level, it is decided by the utility. If you do a big power plant of photovoltaic generation, it is an agreement with the utility where you are, but for the small-scale residential installation, it is the interconnection requirement that is standardized that will resolve that.
That report you cited, if I recall properly, was a few years ago. Right now, the review of the actual standard will hopefully solve the problem. We obviously don't control the end result of a committee like that, but we're actively involved to make sure that it's harmonized with the U.S. side of interconnection, which is also under review right now.