I understand that, Mr. Maki, but on a $12-billion project, you would have had some firm fixed-pricing, some fixed contracts.
How do you then move from $12 billion to $20 billion to $30 billion to $34 billion, if you have fixed contracts with vendors, with suppliers and with contractors? How in the world does that change?
I come from a contracting background.