The project was filed in 2013. It was recommended by the NEB that it be approved. It was approved by the Prime Minister in 2016. The investment decision was announced in 2017 by Kinder Morgan, and then costs started to escalate because there was unreasonable regulatory risk. That continued to move until the federal government decided.... Kinder Morgan suspended non-essential spending on the project in April 2018. There was too much regulatory uncertainty for them to proceed and to continue to take that risk to get the project done. That's what happened.