Thank you.
For the pipeline itself, I'm going to drill into some numbers here.
When the government bought this pipeline, it was supposed to cost $7.4 billion for the expansion when it was under Kinder Morgan. In 2020, you estimated that was up to $12.6 billion because it was suddenly more expensive. In 2022, your number was $21.4 billion, and now that number, as it turns out, is $34.2 billion. It's increased by a factor of five times, so this is a significant increase.
If you look at a comparable pipeline, you see that the CGL up in northern B.C. went up by almost a factor of two, not five. You can talk about engineering, but that was a new pipeline and a new route.
I think Canadians want to know, Mr. Giroux, where the money went.