Thank you, Mr. Chair. That's a great question for us.
The project that was approved by Highrock Resources is the only project we have submitted in the first two rounds to the ERF and have executed. For that project in particular, it was completed at an oil production facility in a region of southeast Saskatchewan that currently has limited gas pipeline infrastructure in place.
Prior to completing the project, we did not have a method to economically conserve the solution gas that was being produced. It was previously venting off multiple devices at the facility, which we were routing to a flare for destruction to help limit the emissions. Our project redirected that vented solution gas into a brand new 10-kilometre pipeline so that it could be processed and utilized.