Indeed, we were then at the planning stage aimed at establishing if the investment would be advantageous or not. The client had already expressed his needs and we were working jointly with him. At the time, we received from the office of Mr. Gagliano or Mr. Jean-Marc Bard a request not to issue a call for tenders for this space. We were asked to wait for directives before going forward.
We still continued our analysis because we had a preliminary step to conclude. According to the timetable, we had to be able to leave the building by April 1, 2003. Going backwards, the call for tenders had to be issued at the latest at the beginning of September 2001, if I am not mistaken.