I may.
Those costs refer to the delay and other costs associated with the new system that was under development. There are two information systems. CFIS I, or Canadian firearms information system I, is the system that has been in place since the outset of the program, and it is the system that continues to provide support to the program. The CFIS II costs were associated primarily, as you have observed, with delay, and the delay costs, to correct the record, were $1.2 million per month.
There were also some associated development and interest charges. These were the cost of not being able to complete the development and delivery. The contractor had incurred expenses of experts, licences, and what have you necessary to develop a new system, and we were not able to proceed.
That answers your question I think in that those costs were incurred because of the delay, and had that system not been under development then, of course those costs would not have been incurred in their entirety.