It was interesting to hear Mr. Wrzesnewskyj refer to the work of the Auditor General as “fictitious extrapolation” earlier. I'll leave it at that.
The Auditor General's report clearly says this decision cost taxpayers $4.6 million. You said you saved $1 million in moving costs, so that makes a net waste to taxpayers of $3.6 million.
In your mind, is the threshold for accountability, when it comes to wasting taxpayers' dollars, somewhere between $3.6 million and $4.6 million? You're saying it's okay to waste $3.6 million. You're making the argument, “Hey, it didn't cost $4.6 million. We actually saved $1 million in moving costs, so it only cost $3.6 million to the taxpayers.” Is that okay?