As we stated earlier, we can't speculate without having a guarantee from a client that somebody is going to move into the space. DND decided they couldn't make that guarantee to us, although they requested us to pursue that option. Later they came back and said, we can't guarantee it.
At the same time, the RCMP was looking at options for the renovation of their campus. We then spoke to the RCMP and the RCMP gave to us a commitment letter because they had funds they needed committed from their existing reference level as well.
With that we went back to talk to the owner of the building at the time, which was JDS. I'll tell you, JDS was gun shy in dealing with us because of the time it was taking. They were getting pressure from the Securities Exchange Commission in terms of the writedown of that property that had some tax implications and felt they couldn't negotiate with us.