Thank you very much for the question, and I appreciate your understanding of the context in which we operate.
Just to go a little further on the statement that no money was misspent, I can tell you that NRCan's staff completed a detailed review back in 2006 of all of the dollars claimed by the CEEA Transport organization. That included reviewing evidence of all work completed against 760 promised deliverables that were included under the contribution agreement. So we substantiated the true value against those deliverables and ensured that only work that was completed was paid for. In fact, it's important to note that as part of that due diligence, $800,000 of invoice claims was disallowed.
So I do feel confident that all the funds that were provided to the agency under our contribution agreement in fact reflected work performed.