Thank you, Mr. Chair.
I just wanted to clarify that the figures come from the plans prepared by the departments and agencies. During our audit, we checked whether those organizations had prepared a long-term plan, by identifying the priorities and the critical systems and infrastructures. We noted that three out of five had done it. Those are the cost estimates that they prepared themselves.
Our concern is that the funds that come from the current budget aren't sufficient to meet the future needs. It is therefore important that there be a plan to fund those projects that the departments themselves identify as critical.