A number of different firms are working on the Hill. In the case of the Library of Parliament—Mr. Wright will answer that question—the project was managed by the firm of the original architect, Mr. Fuller. More specifically, the work was carried out by PCL, Fuller and Pomerleau.
We contract with different firms for different projects. Briefly, when we go forward with a project proposal, we call for bids to ensure the best possible price and the best possible work. So then, different firms may be retained. That said, these were the three firms hired to oversee the work at the Library of Parliament.