For the major rehabilitation of the West Block, for example, we will be going forward in the fall for new government authorities to be able to go out for tender to begin the major rehabilitation. We expect to be able to start the project this fall, and then tranche by tranche we will go out for additional contracts. To be able to accelerate the project as quickly as possible, we have the project broken up into parallel streams of activities that are based on our discussions with expert consultants in the scheduling and costing areas to make sure we have probity from both a fiscal and a timeline perspective.
On June 15th, 2010. See this statement in context.