This assessment, this third-party review by Deloitte, has been completed. The finding of the third-party review is that accelerating the construction of the West Terrace Pavilion would be a high-risk strategy, in the sense that it could cause delays to the rehabilitation of the core historic parliamentary buildings from a time perspective and from a space perspective. As you saw last week, we are relocating facilities off of the Hill. The West Terrace Pavilion does not have enough capacity to be a replacement for that interim relocation strategy, so from both a timing and a space perspective, it was deemed a high-risk strategy.