Thank you, Mr. Chair.
On the economic action plan, the need for speed required that the government rely on assumptions at the beginning, so some of those assumptions were around the fact that they would approve projects that were ready to go. So they relied on attestations from the proponents. One of the assumptions would be that this information would be accurate, and the other assumption related to that would be that if something started on time, it would finish on time. What we've noted, as the member raises, is that some of the projects are running late. During the audit, the government was certainly aware of this and was monitoring those. The final impact is yet to be known, whether or not those will miss the deadline. We don't know that. We'll see in our next audit.