Out of the 410 we sampled, it ranged from program to program, as far as those that started late were concerned. What we looked at was a comparison of the date that was in the application as to when they were supposed to start versus the date of when they actually started. It ranged anywhere from 5% to 40%, depending on the projects, and those delays could be for a number of different reasons.