Thank you for your question.
The $235-million settlement that was negotiated with SSL is the only claim that would increase the cost. Currently, there are no others, and we aren't aware of anything else that could increase the cost of building the bridge.
As part of the negotiated $235-million settlement, SSL assumed responsibility for potential delays in the bridge's opening. It is contractually obligated to complete the bridge by December 21, 2018, and if the bridge isn't ready by then, SSL will have to comply with the requirements set out in the contract.