Thank you for your question.
There were two key dates in the implementation of the new system. The first one was October to be ready and then to be ready for audit April 1. We were ready in both cases. The system was in place by October 1. We were ready for audit on April 1.
We were informed recently that the audit will take place in the fall, in September 2016, I believe.
In order to satisfy ourselves of our readiness, we launched an audit ourselves through EEM. A third party firm conducted an audit. We will have the report tomorrow, but early indications are that we are in full compliance with the requirements.
Any adjustments will be made between now and the official audit that will take place in September.