Very good. Thank you, sir.
I'll move on to another matter that's been raised on which I'd like to follow up. It's the business of the projected savings being removed from the budget before the savings were actually in place. There was a three-year plan. You had a baseline of $128 million. You were projecting to save $72 million a year in a three-year plan. The plan was delayed by at least a year, and yet you went ahead and took the $56 million out of the 2015-16 fiscal year.
First, I'd like to know why you did that before you had actually achieved the savings. Second, what are the implications and collateral damage from having removed that money before you should have?