While I acknowledge that the Public Health Agency rightfully needed to make the overarching contract more flexible, given the evolving nature, that's where task authorizations then become really important to pull down off of this broader contract when you're asking for something specific. That's when you should be specific about the level of effort, who should be doing it and the skills that you need. Creating flexibility in one area still means that you need to provide some specificity for good accountability in another.
On February 20th, 2024. See this statement in context.