I appreciate that. I would be interested in that and eager to hear a follow-up specifically on the municipal drainage issue.
Turning now briefly to the report, exhibit 4.6 talks about “incomplete or missing” performance measures. It breaks them down by national projects and then, specifically, Arctic and northern projects. I would say it's pretty concerning that only 5% of northern or Arctic projects had a complete performance measurement strategy in place, and the remaining 95% of those projects that the Auditor General's office studied had some form of incomplete information, whether it was indicators, the target or the baseline.
I'm curious to know, in the immediate term, since you've had this report, if any of that additional information has been found. Has that been brought to light to try to reassure folks that there are actual measurements being taken for these Arctic and northern projects, which I would say are especially important for northern communities?