I'll start with reiterating the fact that we identified that long-standing issues hadn't been addressed in our report. However, I would say that the efforts taken to extend the life of some of the equipment so that time is available for the new equipment to be purchased are a good step. Mind you, there's not a lot of time to spare if there are further delays.
In terms of other positives, I would say that, at this point in time, the work that's being done by the departments to consider contingencies—the bringing on of a third shipyard—is a positive development. However, again, we've seen that with the previous shipyards it took seven years after the agreements were negotiated for a ship to be produced, so time is running out.