Yes, thank you.
We said that the costs, early design and conceptual work were well managed. We said that, at this point in time, the department has kept spending below the approved amounts, which is important. Up to the point in time when our audit was completed, which was a little while ago now, they were on schedule.
We did issue a bit of a warning flag. As time moves on, and despite the flexible approaches the department has taken to date, if there are changes to user requirements or big adjustments required, they will have an impact on costs moving forward. We wanted to make sure that signal was out there, as well.