In 2002 that audit was really related to the costs, and the disclosure of the increasing costs to Parliament. We did not do a lot of work on the actual operations of the program.
In 2006 we looked to see if the recording of the costs...and the allocation of the costs as well was an issue we looked at in 2006. We saw that had improved. We looked at the centre, because it was really a separate department that had been established, and at how the operations of that centre were operating. We found again that there had been improvement.
Generally a performance audit to look at that program would take us a year to a year and a half to do.