I'll take the second question first, if I may.
I feel very confident that the costs in this case were justified. Based on the formula we use to secure every site, as far as RCMP costs go, we projected $507 million. We have spent, as of a month or so ago, $329 million of that $507 million.
On what we are waiting for, without getting into it too much, we have some MOUs with municipal partners that still have to come in--Toronto Police Service. But we're going to be able to sell some of the assets we purchased and recoup some money. So the number is fluctuating a little, and that's why we can't give you an exact number right now. But it was $329 million up to the end of August.