For the smaller study we did of around 200 buses when we were going to convert a facility, we did do a detailed costing of that, and the payback period of that was around six years.
On May 1st, 2012. See this statement in context.
On May 1st, 2012. See this statement in context.
Manager, Transit Fleet, Calgary Transit
For the smaller study we did of around 200 buses when we were going to convert a facility, we did do a detailed costing of that, and the payback period of that was around six years.