I'd just add that the Broadway costs also include rolling stock for the entire network, additional SkyTrain cars for the entire SkyTrain system.
There are a couple of other things the city's doing. We've strategically purchased property along the line for all of the station locations that will be needed. The corridor is in the street right-of-way. Then where the Broadway line starts up, we've negotiated with the developer to provide land for staging and all the construction needs at the start of the project. We've been proactively securing the land and right-of-way so those don't become additional project costs. That will be our contribution to the project.