Similar to the mayor's comments, now, of that phase one program, we have under contract I think the equivalent of about 53% of the dollars, even though we've only sent invoices to the federal government for less than a quarter of that. We have those contracts under way. As we understand it, the economic activity is going. Our fleet that is being built both in Canada and abroad will be arriving later this year, even if it hasn't been built. There is a bit of a lag time.
The extension by a year for the program was helpful for us. I think it recognized that an infusion of this level of spending doesn't necessarily mean that the regional and provincial entities are ready to go, if the dollars aren't there. There's a ramping up of our internal resources, to be able to do so, to make sure that all of the estimates for projects are current, etc. There's a lot of background work that needs to happen to thus get them out the door. However, once that goes, things can move quite quickly.