It will be structurally complete before the end of December. Signature sur le Saint-Laurent did a technical briefing with us and the minister on October 25 to try to be very transparent on the status of the bridge and the advancements of the construction.
I mentioned that you can walk across it, and that's because all of the major components of the bridge will be in place before the end of December, which reduces the construction risk. Then from there, as I mentioned, certain work such as asphalt, weatherproofing and waterproofing can't be done until the temperature and humidity factors are correct. But with the days that they need to complete that, they are sure they can complete it before the end of June.