Thank you for the question.
Weather is the biggest factor. Some work can't be done in the rain or cold. The bulk of the construction will be completed in December, leaving the work that couldn't be done during the winter for the spring. Taking into account the weather and the number of days necessary to complete the work, we can confirm that the bridge will open no later than the end of June, but likely sooner.