Thank you, Madam Chair.
Just to answer my colleague across the way, and correct me if I'm wrong, Infrastructure Canada, according to the PBO report, the lapsed funds of $727 million were primarily due to delayed spending on infrastructure projects. That's a significant amount of money that was lapsed by you guys because of the delays.
The sums of $100,000 per day, $400,000 per day after the first week, $150 million maximum are agreed to in the contract with the Champlain Bridge. Are we going to be recovering that money?