To date, our partner, the Signature on the Saint Lawrence (SSL) group has not changed the deadline for opening the bridge. It is still planned for the end of June 2019. The bridge is now finished—I could walk from one end to the other—but it is not open yet. That being said, most of the major work has been completed.
During the winter, we cannot work on some features of the bridge. You need good weather conditions for some of the work, such as the
weatherproofing and putting the final asphalt on. That will be done in the spring.
At this point in time, SSL continues to confirm to us that the opening of the bridge will not be later than the end of June 2019. We do have an independent engineer who looks at the schedules who has also confirmed to us that we are on track. There is nothing to make us believe that that wouldn't be the case.