Thank you for that question, and through you, Madam Chair, you're absolutely right. One of the reasons we removed the condition of P3 screening was to allow municipalities to make their own decisions. The other thing you have identified is that it limited the funding for municipalities to 25% of the total eligible project costs. Under the traditional model, municipalities would receive up to one-third, and in some cases up to 50%, depending on the project. Under the P3 approach, there was a limit of 25%.
As we move forward on removing the condition of P3, we will be adjusting that cost-sharing formula for major projects that fall under that big project category.