What we can do will vary, depending on the type of program that we have, as well as the stage and phase of the project and where it's at. For that particular project—although I don't know the details of it—the proponents can certainly follow up with us, and we'd be happy to work with them on determining what the options could be.
Do we have funds on the side for cost escalation? No, but what we can often do is look at different options, whether it's phasing or future opportunities. As well, within ICIP—the investing in Canada infrastructure program—we might have different opportunities, so what we can or cannot do really depends on the program as well as the stage of the project.